Item Coversheet

*4.C.1.


Shakopee City Council
AugustĀ 21, 2018


FROM:Ryan Halverson, Assistant City Engineer
TO:Mayor and Council Members
Subject:
Accept Work on the 2017 Bituminous Overlay Improvements Project 2017-2.
Policy/Action Requested:

Approve Resolution R2018-089, accepting work on the 2017 Bituminous Overlay Improvement project 2017-2 and make final payment of $50,561.14.

Recommendation:

Approve Resolution R2018-089.

Discussion:

On April 4, 2017, City Council adopted Resolution 7885, a resolution accepting the bids and awarding the contract for the 2017 Bituminous Overlay Project to Wm Mueller & Sons of Hamburg, Minnesota.

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $1,152,305.71 and the actual final contract costs of $989,420.39. The remaining amount left to pay is $50,561.14, which was held as retainage.

Budget Impact:

The total final project amount is $1,038,230.07. This total includes the final construction cost of $989,420.39 and engineering/administration/legal costs amounting to $48,809.68.

 

This project is funded by the Capital Improvement Fund (CIF), Storm Drainage Fund, Sanitary Sewer Fund, and Shakopee Public Utilities Water Fund as follows:

 

 

 

Project Completion

   

Capital Improvement Fund

$1,006,974.07

Sanitary Sewer Fund

$       8,995.00

Storm Sewer Fund

$       8,995.00

Shakopee Public Utilities

$     13,266.00

Total Costs

$1,038,230.07