| | | | | | | |  Shakopee City Council October 16, 2018
|
| | | | | | | | | FROM: | Ryan Halverson, Assistant City Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject: Declare Costs to be Assessed and Adopt the Assessments for 225 Sommerville Street South Sanitary Sewer Extension. | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2018-119 declaring costs to be assessed, and adopt Resolution R2018-120, adopting assessments for the 225 Sommerville Street South Sanitary Sewer Extension Project. | | |
| | | | | | | | Recommendation:
Adopt Resolutions R2018-119 and R2018-120. | | |
| | | | | | | | Discussion:
On July 17, 2018, City Council adopted Resolution R2018-083, accepting quotes and awarding the contract for the Sommerville Alley Sewer Extension Project.
The improvements have been constructed and are now complete. The contract construction costs are $49,019.00 and engineering/administration/legal costs are $7,723.72 resulting with a final total project cost of $56,742.72. The attached resolution declares total project costs, the final project funding amounts, and the total cost to be assessed.
An agreement for payment of special assessments for a portion of this project by the property owner of 225 Sommerville Street South in the amount of $12,500.00 was executed by the property owner and the city on October 17, 2017. Through this agreement, the property owner also waived the right to a public hearing for special assessment. Additionally, a Scott County grant in the amount of $6,000 will be used to fund a portion of the public sewer extension project as part of the Minnesota Pollution Control Agency grant funding available to remove old septic systems.
| | |
| | | | | | | | Budget Impact:
This project is substantially complete, project costs are identified, and only minor miscellaneous punch list items remain to be completed. The final project cost is $56,742.72, which includes construction and engineering/administration/legal costs. A breakdown of the project funding is as follows:
|
|
|
Project Estimate |
Project Completion
|
|
Assessments
|
$ 12,500 |
$ 12,500
|
| Scott County Grant |
$ 6,000 |
$ 6,000
|
|
Sanitary Sewer Fund
|
$ 33,481 |
$ 38,242.72
|
| |
|
|
|
Total Costs
|
$ 51,981 |
$ 56,742.72
|
|
|
|
| | |
|