Valley Park 11th Addition Drainage Channel Improvement Project 2017-7.
Policy/Action Requested:
Accept work on the Valley Park 11th Addition Drainage Channel Improvement Project 2017-7 and authorize final payment of $6,707.88.
Recommendation:
Accept work and authorize final payment.
Discussion:

During the summer of 2016, the drainage way and spillway area between 12th Avenue and Highway 169 experienced significant erosion (see attached location map). In response, an emergency project was developed that  included repairing the existing pond overflow and extending the outlet pipe to reduce the risk of future continued erosion and spillway failure.

 

On May 2, 2017, City Council reviewed two quotes and awarded a contract for the project to Krueger Excavating of Prior Lake, Minnesota, in the amount of $62,096.00 with an authorized 15% contingency amount. The original engineers estimate for the construction was $51,000.

 

To date, all of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $62,096.00 and the actual final contract costs of $66,327.67. The final payment amount is $6,707.88, which includes the final  contract work completed in summer 2018 and the remainder of the retainage. The final contract amount is 6.8% over the original contract amount, but within the authorized contingency amount.

Budget Impact:
All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $62,096.00 and the actual final contract costs of $66,327.67. The remaining amount left to pay is $6,707.88, which was held as retainage.
The total final project amount is $76,270.71. This total includes the final construction cost of $66,327.67 and engineering/administration/legal costs amounting to $9,943.04. This project is funded by the Storm Drainage Fund.