| | | | | | | |  Shakopee City Council March 5, 2019
|
| | | | | | | | | FROM: | Ryan Halverson, Assistant City Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject: Approve Plans and Order Advertisement for Bids for the 2019 Street & Utility Reconstruction Project. | | |
| | | | | | | | Policy/Action Requested: Approve Resolution R2019-030, approving plans and ordering the advertisement for bids for the 2019 Street & Utility Reconstruction Project CIF-19-003. | | |
| | | | | | | | Recommendation: Approve Resolution R2019-030. | | |
| | | | | | | | Discussion:
On February 19, 2019, a public improvement hearing was held and Resolution R2019-017 was approved by City Council ordering the 2019 Street & Utility Reconstruction Project. The project includes the reconstruction of Scott Street from 4th Avenue to 6th Avenue, Minnesota Street from 4th Avenue south to the end of the cul-de-sac, and 7th Avenue from Sommerville Street to Spencer Street.
Plans have been prepared as directed and are ready to solicit public bids to construct the improvements. Upon approval, the advertising and bidding will commence with a scheduled bid opening in April 2019. Bids would then be considered, currently anticipated for the April 16, 2019, City Council meeting. Construction of the improvements will be performed between May and September of 2019. | | |
| | | | | | | | Budget Impact: The project will be funded by the Capital Improvement Fund, Sanitary Sewer Fund, Surface Water Fund, Shakopee Public Utilities, and Special Assessments as presented in the project's feasibility report. | | |
|