Item Coversheet

*4.D.3.


Shakopee City Council
March 19, 2019


FROM:Ryan Halverson, Assistant City Engineer
TO:Mayor and Council Members
Subject:
12th Avenue Reconstruction Project CIF-19-004.
Policy/Action Requested:
Approve Resolution R2019-034, approving plans and ordering the advertisement for bids for the 12th Avenue Reconstruction Project CIF-19-004. 
Recommendation:
Approve Resolution R2019-034.
Discussion:

On August 8,2018, City Council authorized the execution of a professional services agreement with SRF Consulting Group, Inc., for design services for the 12th Avenue Reconstruction Project CIF-19-004.

 

Plans have been prepared as directed by city staff and are ready to solicit public bids to construct the improvements. Upon approval, the advertising and bidding will commence with a scheduled bid opening on April 25, 2019. Bids would then be considered, currently anticipated for the May 7, 2019, City Council meeting. Construction of the improvements will be performed between May and November of 2019.

Budget Impact:
The project is budgeted in the 2019 Capital Improvement Plan as part of the Canterbury Commons Development Tax Increment Funding.
ATTACHMENTS:
Description
Resolution R2019-034
plans