Discussion:
Community Center Gym project PA-19-07 was programmed in CIP for Summer 2019 at $50,000.00. The project is planned for late-August upon completion of Summer Programs and prior to start of Fall Programs. Approving the preferred vendors listed below will reduce the project cost to $35,036.00.
Painting: Schoenfelder is preferred vendor with bid of $24,971.00 which was lower than Future City with bid of $43,866.88.
Pipe Insulation: K-Factor is preferred vendor with bid of $7,020 which is lower than Enervation with bid of $8,740.00.
Floor Refinish: American Sports Floors is the only vendor that can complete the project in the timeframe with bid of $3,045.00.