2016 Sanitary Sewer Lateral Pipe Rehabilitation Project 2016-6

 

Policy/Action Requested:
Approve Resolution R2019-104, accepting work on the 2016 Sanitary Sewer Lateral Pipe Rehab Project 2016-6 and make a final payment of $39,676.09.
Recommendation:
Approve Resolution R2019-104.
Discussion:

On July 5, 2016, City Council adopted Resolution No. 7745 accepting the bids and awarding the contract for the  2016 Sanitary Sewer Lateral Pipe Rehabilitation to BLD Services, LLC., of Kenner, Louisiana. 

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $524,980.00 with actual final costs of $417,473.75. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to BLD Services, LLC., in the amount of $39,676.09.

Budget Impact:

The total final project amount is $583,430.62. This total includes the final construction cost of $417,473.75 and engineering/administration/legal costs amounting to $165,956.87. This project is funded by the Sanitary Sewer Fund as follows:

 

 FUNDING       CIP Estimate  Project Completion
Sanitary Sewer Fund $           750,000.00 $          583,430.62 

 