FROM:Steve Lillehaug, City Engineer/Public Works Director
TO:Mayor and Council Members
Subject:
Public Hearing for the Wood Duck Trail Reconstruction Project CIF-19-008.
Policy/Action Requested:
Adopt Resolution R2019-114, adopting assessments for the Wood Duck Trail Reconstruction Project CIF-19-008.
Recommendation:
Adopt Resolution R2019-114.
Discussion:

On July 16, 2019, City Council adopted Resolution R2019-073, approving the plans and specifications and ordering the advertisement for bids for the Wood Duck Trail Reconstruction Project CIF-19-008. On August 20, 2019, City Council adopted Resolution R2019-088, accepting the bids and awarding the contract for the Wood Duck Reconstruction Project. 

 

The project has subsequently been completed, and on October 15, 2019, City Council adopted Resolution R2019-108, declaring the costs to be assessed, ordering the preparation of proposed assessments and setting a public hearing date for November 6, 2019, for the Wood Duck Trail Reconstruction Project CIF-19-008.

 

As indicated, this project is substantially complete, project costs are identified, and only minor miscellaneous punch list items remain to be completed. City policy is to assess 30% of the street improvements to the benefiting properties. Properties are recommended to be assessed in accordance with the preliminary engineering report. Accordingly, the computed assessment rate is $14,706 per lot. However, based on the special benefit appraisal analysis conducted for this project, the final assessment amount is recommended to be capped at $12,000 per unit/lot, noting that corner lots are assessed at 50 percent of the regular lot amount.

 

Attached to this memo is a map of the project area and the assessment roll for Council consideration and adoption. A presentation of the final costs and assessments will be made at the Council meeting.

Budget Impact:

The final project cost is $370,362.88, which consists of construction and engineering/administration/legal costs. The following Costs and Funding Summary provides the estimated amounts based on bid award and the final project amounts based on actual costs.

 

Estimated Based On Actual
Bid Award Final Amounts
COSTS
Construction Cost $ 335,908.20 $336,302.80
Contingency $ 30,000.00 $5,000.00
Subtotal $ 365,908.20 $ 341,302.80
Eng/Admin/Legal $ 33,100.00 $29,060.08
Total Project Cost $ 399,008.20 $ 370,362.88
FUNDING
Capital Improvement Fund $ 299,608.20 $ 277,162.88
Special Assessments $ 66,000.00 $ 66,000.00
Storm Drainage Fund $33,400.00 $27,200.00
Total Funding $ 399,008.20 $ 370,362.88