Discussion:
The city's Capital Improvement Plan (CIP) contains the 2020 Sewer Service Lateral Pipe Rehabilitation Project Sewer-20-003, consisting of cured-in-place lateral lining of sanitary sewer services under various streets throughout the city (see attached CIP summary sheet). The city has successfully completed similar lateral lining projects in 2015, 2016, 2018 and 2019. This is a continuation of the lateral lining program to maintain existing sanitary sewer infrastructure, prevent potential damage to city streets, and avoid expensive repairs for residents when sanitary sewer service failures occur.
This is the final year of the Sewer Service Later Pipe Rehabilitation Program. Plans have been prepared as directed and public bids are ready to be solicited to construct the improvements. Upon approval, the advertising and bidding will commence with a scheduled bid opening of approximately February 27, 2020. Bids would then be considered at the March 17, 2020 City Council meeting. Construction of the improvements will be performed between July and November of 2020.