Discussion:
On March 7, 2017, City Council adopted Resolution No. 7844, which approved the plans and specifications and authorized staff to advertise for bids for the 2017 Street Reconstruction, Project 2017-1.
On April 11, 2017, a bid opening was held for the 2017 Street Reconstruction Project, in which there were eleven bids opened for this reconstruction project. The bids are summarized in the attached resolution. From the bid opening, the low bidder is Kuechle Underground Inc. with a bid of $1,666,751.40. The feasbility report construction cost estimate for this project is $2,089,000.00.
The Preliminary Engineering report included a project cost estimate of $2,582,000.00. Adding a 5% contingency to the low bid and 18% indirect costs, the projected project cost is approximately $2,000,101.68.
If Council awards the contract, staff is also requesting a contingency amount equal to 5% of the contract to cover minor change orders and quantity adjustments that may occur on the project.