Discussion:
The replacement of the trailer mounted portable sewer pump is included in the 2020 Capital Improvement Plan (see attached CIP summary sheet Sewer-20-016). The pump is used for emergency pumping of sanitary sewer and storm sewer (flooding) as needed, most notably it is the backup pump for the city's Lift Station #16.
Bids for the portable pump were solicited and received as follows:
Electric Pump $ 121,020.00**
Mn Pump Works $ 98,790.00
Rain For Rent $ 84,827.00**
United Rentals $ 68,000.00**
Note: **Did not meet minimum specifications
The lowest bid meeting all required specifications is from Minnesota Pump Works in the amount of $98,790.00.
The existing pump is well past it's life expectancy but will be kept as a backup.