Shakopee City Council
May 2, 2017


FROM:Bruce Loney, Public Works Director
TO:Mayor and Council Members
Subject:
Award a contract for the Whispering Oaks Sanitary Sewer Extension Project 2017-3
Policy/Action Requested:
Approve Resolution 7878 which accepts the bids and awards a contract for Project 2017-3 to Northwest Asphalt, Inc. and approve a 5% contingency amount on the project for use by the City Engineer in authorizing change orders or quantity adjustments. Also, to authorize the appropriate city officials to execute an extension agreement with Bolton & Menk, Inc. for construction engineering services.
Recommendation:
  • Adopt Resolution 7878.
  • Approve a 5% contingency amount by the City Engineer for change orders and quantity adjustments.
  • Authorize an extension agreement with Bolton & Menk, Inc. for construction engineering services.
Discussion:

On March 7, 2017, City Council adopted Resolution 7845 which approved the plans and specifications and authorized staff to advertise for bids for the Whispering Oaks Sanitary Sewer Extension, Project 2017-3.

 

On April 25, 2017, a bid opening was held on the project, in which there were six bids opened. The bid proposals had a bid Part A (sanitary sewer only) and a bid Part B (sanitary sewer and watermain). The bids are summarized in the attached resolution.

 

For the bid opening, the low bidder for Part A and Part B bid packages is Northwest Asphalt, Inc. with bids of $644,013.90 and $785,984.90, respectively. Shakopee Public Utilities is considering the bids at its May 1, 2017 meeting. If the Commission does not want to proceed with the watermain, Resolution 7878 would be revised to recommend Bid Package A.

 

The engineers estimate was $700,000.00 (A) and $900,000.00 (B), respectively.

 

If Council awards the contract, staff is requesting a contingency amount of 5% of the content to cover minor change orders and quantity adjustments that may occur on the project. Also an extension agreement with Bolton & Menk, Inc. is needed for construction engineering services such as surveying.

Budget Impact:
This project is funded by the Sanitary Sewer fund.