Subject:
Award a contract for the Whispering Oaks Sanitary Sewer Extension Project 2017-3
Policy/Action Requested:
Approve Resolution 7878 which accepts the bids and awards a contract for Project 2017-3 to Northwest Asphalt, Inc. and approve a 5% contingency amount on the project for use by the City Engineer in authorizing change orders or quantity adjustments. Also, to authorize the appropriate city officials to execute an extension agreement with Bolton & Menk, Inc. for construction engineering services.
Recommendation:
  • Adopt Resolution 7878. 
  • Approve a 5% contingency amount by the City Engineer for change orders and quantity adjustments. 
  • Authorize an extension agreement with Bolton & Menk, Inc. for construction engineering services.
Discussion:

On March 7, 2017, City Council adopted Resolution 7845 which approved the plans and specifications and authorized staff to advertise for bids for the Whispering Oaks Sanitary Sewer Extension, Project 2017-3.

 

On April 25, 2017, a bid opening was held on the project, in which there were six bids opened. The bid proposals had a bid Part A (sanitary sewer only) and a bid Part B (sanitary sewer and watermain). The bids are summarized in the attached resolution.

 

For the bid opening, the low bidder for Part A and Part B bid packages is Northwest Asphalt, Inc. with bids of $644,013.90 and $785,984.90, respectively. Shakopee Public Utilities would install the watermain if the cost is less than $70,000. The cost is approximately $85,000, thus SPU does not want to move forward. Resolution 7878 is recommending Bid Package A for sanitary sewer only.

 

The engineers estimate was $700,000.00 (A) and $900,000.00 (B), respectively. 

 

If Council awards the contract, staff is requesting a contingency amount of 5% of the content to cover minor change orders and quantity adjustments that may occur on the project. Also an extension agreement with Bolton & Menk, Inc. is needed for construction engineering services such as surveying.

Budget Impact:
This project is funded by the Sanitary Sewer fund.