| | | | | | | |  Shakopee City Council JuneĀ 6, 2017
|
| | | | | | | | | FROM: | Rick Thomson, Project Coordinator | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject: Accept Work on the 2014 Bituminous Trail Improvements Project No. 2014-7 and 2013-3. | | |
| | | | | | | | Policy/Action Requested:
Approve Resolution 7893, accepting work on the 2014 Bituminous Trail Improvements for projects 2014-7 & 2013-3. | | |
| | | | | | | | Recommendation: Staff recommends approving resolution 7893 which directs final payment of $32,262.76; therefore accepting the work on the 2014 Bituminous Trail Improvements Project No. 2014-7 & 2013-3. | | |
| | | | | | | | Discussion: All of the work for this project has been completed in accordance with the contract documents. Attached is a Certificate of Completion showing the original contract amount of $560,728.40 and the actual final costs of $511,875.25. The remaining amount left to pay is $32,262.76. | | |
| | | | | | | | Budget Impact: This project is funded by a combination of County funds, SMSC Donation, Surface Water Fund and Capital Improvement Fund. | | |
|