Item Coversheet

*4.E.1.


Shakopee City Council
February 2, 2021


FROM:Ryan Halverson, Assistant City Engineer
TO:Mayor and Council Members
Subject:

2020 Trail Rehabilitation and Trail Reconstruction Projects, CIF-20-001 and PA-20-01.

 

Policy/Action Requested:
Approve Resolution R2021-010, accepting work on the 2020 Trail Rehabilitation and Trail Reconstruction Projects, CIF-20-001 and PA-20-01, and authorize final payment of $2,196.16.
Recommendation:
Approve Resolution R2021-010.
Discussion:

On June 2, 2020, City Council adopted Resolution R2020-073 accepting the bids and awarding the contract for the 2020 Trail Rehabilitation and Trail Reconstruction Projects to Bituminous Roadways, Inc., of Mendota Heights, MN. 

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $216,299.65 with actual final costs of $219,615.42. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to Bituminous Roadways, Inc., in the amount of $2,196.16.

Budget Impact:

The total final project amount is $257,052.40. This total includes the final construction cost of $223,528.28 and engineering/administration/legal costs amounting to $33,524.12. This project is funded by the Capital Improvement Fund (CIF) and Park Asset Fund as follows:

 

 

Estimated

(Contract Award)

Actual

(Final Contract)

Construction Contract

$ 216,299.65 $ 219,615.42

Contingency

$   17,300.00

$     3,912.86
Subtotal $ 233,599.65 $ 223,528.28

Eng/Ad/Legal

$   30,000.00

$   33,524.12

Total Costs

$ 263,599.65

$ 257,052.40

 

Funding Source

Estimated

(Contract Award)

Actual

(Final Contract)

Capital Improvement Fund

$ 217,286.23

$ 211,889.31

Park Asset Fund $   46,313.42  $   45,163.09
   

Total Funding

$ 263,599.65 $ 257,052.40
ATTACHMENTS:
Description
Resolution R2021-10
Certificate of Completion