| | | | | | | |  Shakopee City Council December 7, 2021
|
| | | | | | | | | FROM: | Nate Reinhardt, Finance Director | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Policy/Action Requested: None | | |
| | | | | | | | Recommendation: Informational Only | | |
| | | | | | | | Discussion:
These reports reflect the expenditures as recorded for 2021 activity. The following transactions are notable for this reporting cycle:
- Frattalone Company Inc: Estimate voucher #7, Ridge Creek Park & PLOC Improvement project. $535,933.09
- Pump and Meter Services Inc: Partial payment for purchasing hardware/software to replace the existing fuel and vehicle wash control system. $44,054.14
- St Croix Recreation Inc: Partial payment for demolition, relocation and construction of a new playground at Scenic Heights. $213,740.69
Included in the check list are various refunds, returns, and pass through. | | |
| | | | | | | | Budget Impact:
Operating and capital expenditures within the 2021 budget. | | |
|