| | | | | | | |  Shakopee City Council March 2, 2021
|
| | | | | | | | | FROM: | Ryan Halverson, Assistant City Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject: 2021 Street and Utility Reconstruction Project | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2021-025, approving plans and specifications and ordering the advertisement for bids for the 2021 Street and Utility Reconstruction Project CIF-20-007. | | |
| | | | | | | | Recommendation: Adopt Resolution R2021-025. | | |
| | | | | | | | Discussion:
On February 16, 2021, a public improvement hearing was held and Resolution R2021-020 was approved by City Council ordering the 2021 Street and Utility Reconstruction Project. The project includes the street and utility reconstruction for portions of Scott Street, Levee Drive, Fuller Street and the alley between Fuller St and Atwood St north of 1st Ave.
Plans have been prepared as directed and are ready to solicit public bids to construct the improvements. Upon approval, the advertising and bidding will commence with a scheduled bid opening on March 30, 2021. Bids would then be considered, currently anticipated for the April 20, 2021, City Council meeting. Construction of the improvements will be performed between May and September of 2021. | | |
| | | | | | | | Budget Impact: The project will be funded by the Capital Improvement Fund, Sanitary Sewer Fund, Surface Water Fund, Shakopee Public Utilities, and Special Assessments as presented in the project's feasibility report. | | |
|