Item Coversheet

*4.E.7.


Shakopee City Council
AprilĀ 6, 2021


FROM:Darin Manning, Engineering Project Coordinator
TO:Mayor and Council Members
Subject:
SCADA System Upgrades Project Sewer-19-005.
Policy/Action Requested:
Adopt Resolution R2021-054, approving plans and specifications and ordering the advertisement for bids for the SCADA System Upgrades Project Sewer-19-005. 
Recommendation:
Adopt Resolution R2021-054.
Discussion:

On August 18, 2020, City Council authorized the execution of a professional services agreement with AE2S for the design and bidding services for the SCADA System Upgrades Project Sewer-19-005.

 

Plans have been prepared and are ready to solicit public bids to construct the SCADA system upgrades. Upon approval, the advertising and bidding will commence with a scheduled bid opening on May 3, 2021. Bids are anticipated to be considered at the May 18, 2021, City Council meeting. Construction of the improvements will be performed between May and December of 2021.

Budget Impact:

This project is budgeted in the 2021 Capital Improvement Plan.  The Cost and Funding Summary below provides estimated amounts as planned in the 2021 CIP budget and updated estimated amounts. Once bidding is complete, a more precise budget will be determined that is needed to deliver the project.

 

CIP

Updated

Budget Estimate
COSTS
Improvements Cost $395,000
Equipment Supply and Install $320,000
PLC/SCADA Programming $90,000

Elec. Supply and Cloud Hosting

$40,000
Contingency $40,000 $15,000
Subtotal $435,000 $465,000
Eng/Admin/Legal $114,000 $108,000
Total Estimated Cost $549,000 $573,000
FUNDING
Sanitary Sewer Fund $549,000 $573,000
Total Funding $549,000 $573,000

ATTACHMENTS:
Description
Resolution R2021-054
CIP Sheet
Construct Plans