Discussion:
On September 6th the City Council rejected all bid for the Lions Park warming house/shelter and directed staff to make revisions to the plans. On February 7, 2017, the City Council reviewed the revised plans for the Lions Park warming house/shelter and provided staff with feedback on what should be included in the bid package. The bid package includes the revised shelter plan including the garage with two bid alternates. The alternates include steel roofing and an extended open air covered patio.
The proposed timeline for the project:
February 21 Council approval to bid
March 9 & 16 Advertise for bids
April 4 Bid opening at 2:00pm at City Hall
April 18 Award of contract
May 1 Construction begins
September 1 Substantial completion