Discussion:
Tahpah Park has 10 undeveloped acres on its west side. Two baseball fields are planned for this area, a youth 12-13 year old field and a full size baseball field. When reviewing the 2017 Park Reserve projects the City Council identified the construction of one field as a priority project. It was determined that the two fields would be built in two different phases. The first phase would include site preparation for both fields and the construction of the full size baseball field.
The full size baseball field can be used by all ages. The baseball field would also be used by the School District's baseball program with its convenient location next to Joe Schleper Baseball Stadium. During the construction of the high school expansion the practice baseball field was removed and no definitive plans have been completed to build a replacement field at another location. The School District is therefore willing to contribute to the development of the full size field to serve the replacement for the baseball field that was removed. This field would serve the school program and the community.
Project Timeline:
February 21 Council approval to bid
March 2 & 9 Advertise for bids
March 28 Bid opening at 1:00pm at City Hall
April 4 Award of contract
April 17 Construction begins
June 16 Substantial Completion