Item Coversheet

*4.D.1.


Shakopee City Council
July 20, 2021


FROM:Kirby Templin, Water Resource/Environmental Engineer
TO:Mayor and Council Members
Subject:

NW Shakopee Stormwater BMP Retrofit Project.

Policy/Action Requested:
Adopt Resolution R2021-109, accepting work on the Regional Stormwater Treatment BMP at County Government Center Lot A, Storm-22-001, and authorize final payment in the amount of $2,598.93.
Recommendation:
Adopt Resolution R2021-109.
Discussion:

On August 18, 2020, City Council adopted Resolution R2020-096 accepting the bids and awarding the contract for the Regional Stormwater Treatment BMP at County Government Center Lot A Project to S.M. Hentges & Sons, Inc., of Jordan, Minnesota. 

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $243,568.86 with actual final costs of $259,892.89. All required project documentation has been received and is compliant. The project will be closed out upon accepting work with issuance of final payment to S.M. Hentges & Sons, Inc., in the amount of $2,598.93.

Budget Impact:

The total final project amount is $345,991.96. This project is funded by the Storm Drainage Fund. The following table provides a summary of the costs and funding amounts comparing the estimated bid award budget versus the final project costs:

 

Bid Award Estimated Final Project Costs
COSTS
Construction Cost $ 243,568.86 $ 259,892.89
Contingency $   26,431.14 $   10,000.00
Subtotal $ 270,000.00 $ 269,892.89
Eng/Admin/Legal $   80,000.00 $   76,099.07
Total Costs $ 350,000.00 $ 345,991.96

 

FUNDING
Storm Drainage Fund $ 350,000.00 $ 345,991.96
Total Funding $ 350,000.00 $ 345,991.96

 

ATTACHMENTS:
Description
Resolution R2021-109
Certificate of Completion