| | | | | | | |  Shakopee City Council July 20, 2021
|
| | | | | | | | | FROM: | Kirby Templin, Water Resource/Environmental Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject:
NW Shakopee Stormwater BMP Retrofit Project. | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2021-109, accepting work on the Regional Stormwater Treatment BMP at County Government Center Lot A, Storm-22-001, and authorize final payment in the amount of $2,598.93. | | |
| | | | | | | | Recommendation: Adopt Resolution R2021-109. | | |
| | | | | | | | Discussion:
On August 18, 2020, City Council adopted Resolution R2020-096 accepting the bids and awarding the contract for the Regional Stormwater Treatment BMP at County Government Center Lot A Project to S.M. Hentges & Sons, Inc., of Jordan, Minnesota.
All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $243,568.86 with actual final costs of $259,892.89. All required project documentation has been received and is compliant. The project will be closed out upon accepting work with issuance of final payment to S.M. Hentges & Sons, Inc., in the amount of $2,598.93. | | |
| | | | | | | | Budget Impact:
The total final project amount is $345,991.96. This project is funded by the Storm Drainage Fund. The following table provides a summary of the costs and funding amounts comparing the estimated bid award budget versus the final project costs:
|
Bid Award Estimated |
Final Project Costs |
| COSTS |
|
|
| Construction Cost |
$ 243,568.86 |
$ 259,892.89 |
| Contingency |
$ 26,431.14 |
$ 10,000.00 |
| Subtotal |
$ 270,000.00 |
$ 269,892.89 |
|
|
|
| Eng/Admin/Legal |
$ 80,000.00 |
$ 76,099.07 |
| Total Costs |
$ 350,000.00 |
$ 345,991.96 |
|
|
|
|
| FUNDING |
|
|
| Storm Drainage Fund |
$ 350,000.00 |
$ 345,991.96 |
| Total Funding |
$ 350,000.00 |
$ 345,991.96 |
| | |
|