Discussion:
Greystone Construction has requested to begin construction at 6AM rather than the required 7AM for construction of the Shakopee Flats Apartments. Because of unusually hot weather, they are wanting to start earlier in the day for the safety of their workers to minimize heat stroke.
The project is currently at the framing stage so workers are guiding panels into place and installing internal walls. At this stage of construction, there is no protection from the sun for workers.