| | | | | | | |  Shakopee City Council October 19, 2021
|
| | | | | | | | | FROM: | Adam Bentson, Graduate Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject:
Quarry Lake Park Mountain Bike Trail Project Closeout | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2021-147, accepting work for the Quarry Lake Park Mountain Bike Trail Project PR-21-006, and authorize final payment of $2,150.16. | | |
| | | | | | | | Recommendation: Adopt Resolution R2021-147. | | |
| | | | | | | | Discussion:
On March 16, 2021, City Council awarded a contract for the Quarry Lake Park Mountain Bike Trail Project to Pathfinder Trail Building.
All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $201,909.50 with actual final costs of $215,015.44. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to Pathfinder Trail Building in the amount of $2,150.16. | | |
| | | | | | | | Budget Impact:
The total final project amount is $262,325.37. This total amount includes the final construction cost of $215,015.44, material procurement costs of $19,949.13, and engineering/administration/legal costs amounting to $27,360.80. This project is funded by the Park Development Fund. The following table provides a summary of the costs and funding comparing the estimated amount based on bid award versus the final actual amounts.
|
Estimate Amounts |
Actual Amounts |
|
(Bid Award) |
|
| COSTS |
|
|
| Construction Cost |
$201,909.50 |
$215,015.44 |
| Contingency |
$20,000.00 |
$0.00 |
| Material Procurement |
$34,105.00 |
$19,949.13 |
| Subtotal |
$256,014.50 |
$234,964.57 |
|
|
|
| Eng/Admin/Legal |
$25,000.00 |
$27,360.80 |
| Total Project Cost |
$281,014.50 |
$262,325.37 |
|
|
|
| FUNDING |
|
|
| Park Development Fund |
$281,014.50 |
$262,325.37 |
| Total Funding |
$281,014.50 |
$262,325.37 |
| | |
|