Item Coversheet

*4.D.9.


Shakopee City Council
October 19, 2021


FROM:Micah Heckman, Project Engineer
TO:Mayor and Council Members
Subject:
Extended Construction Hours for the Windermere South 5th Addition Development.
Policy/Action Requested:
Approve suspension of City Code Sec. 130.45, Noise Elimination and Noise Prevention, Subd. C.4, Hourly Restrictions on Certain Operations, allowing Windermere South 5th Addition project contractor, Northwest Asphalt and their subcontractors, to perform work from 8 a.m. to 9 p.m. on Saturdays through the end of December 2021.
Recommendation:
Approve the requested action.
Discussion:

City Code Section 130.45 restricts the hours of construction operation from 7 a.m. to 10 p.m. on weekdays, and 9 a.m. to 9 p.m. on weekends and holidays.

 

Contractors working on the Windermere South 5th Addition development project have requested the city to extend working hours to begin work at 8 a.m. on Saturday mornings through the end of December 2021.

 

This extension will help meet the project deadlines. The impacts from the earlier generated noise is not anticipated to be a substantial nuisance in this area of the city for the prescribed times. If property owner complaints are received by the City, the ordinance suspension can be revoked at the discretion of the City Engineer.

 

With Council's approval, a public news release and notice to meet the City Code requirements would be placed in the Shakopee Valley News and on the City's website.

Budget Impact:
None.
ATTACHMENTS:
Description
DRH request for extended construction hours