Item Coversheet

*5.D.8.


Shakopee City Council
March 15, 2022


FROM:Adam Bentson, Graduate Engineer
TO:Mayor and Council Members
Subject:

Memorial Park Trail and Pedestrian Bridge Project Closeout

Policy/Action Requested:
Adopt Resolution R2022-039, accepting work on the Memorial Park Trail and Pedestrian Bridge Project PA-19-09, and authorize final payment of $37,304.68 to S.M. Hentges & Sons.
Recommendation:
Adopt Resolution R2022-039.
Discussion:

On December 1, 2020, City Council awarded a contract for the Memorial Park Trail & Pedestrian Bridge Project to S.M. Hentges & Sons.

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $536,758.65 with actual final costs of $558,299.89. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to S.M. Hentges & Sons in the amount of $37,304.68.

Budget Impact:

The total final project amount is $879,498.59. The project is funded by the Park Asset Internal Service Fund, contributions from the SMSC and Scott County, and DNR grant money. The following table provides a summary of the costs and funding comparing the estimated amount based on bid award versus the final actual amounts.

 

Estimate Amounts Final
(Bid Award) Actual Amounts
COSTS
Construction Cost $536,758.65 $558,299.89
Contingency $75,000.00 $48,099.00
Subtotal $611,758.65 $606,398.89
Eng/Admin/Legal $265,000.00 $273,099.70
Total Project Costs $876,758.65 $879,498.59
     
FUNDING
State DNR grant $300,000.00 $300,000.00
SMSC $100,000.00 $100,000.00
Scott County $50,000.00 $50,000.00
Park Asset Internal Service Fund $426,758.65 $429,498.59
Total Funding $ 876,758.65 $ 879,498.59

ATTACHMENTS:
Description
Resolution R2022-039
Certificate of Completion