| | | | | | | |  Shakopee City Council March 1, 2022
|
| | | | | | | | | FROM: | Adam Bentson, Graduate Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject:
Red Oak Trail Project | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2022-030, accepting work on the Red Oak Trail Project PR-20-005, and authorizing final payment in the amount of $22,521.72 to Max Steininger, Inc. | | |
| | | | | | | | Recommendation: Adopt Resolution R2022-030. | | |
| | | | | | | | Discussion:
On June 15, 2022, City Council adopted Resolution R2021-076 accepting the bids and awarding the contract for the Red Oak Trail Project to Max Steininger, Inc., of Eagan, MN.
All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $178,795.88 with actual final costs of $176,166.80. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to Max Steininger, Inc. in the amount of $22,521.72. | | |
| | | | | | | | Budget Impact:
The total final project amount is $201,725.52. This project is funded by the Park Development Fund and Tree Replacement Fund. The following table provides a summary of the costs and funding amounts comparing the estimated bid award budget versus the final project costs:
|
|
Bid Award Estimated
|
Final Project Costs
|
|
COSTS
|
|
|
|
Construction Cost
|
$ 178,795.88
|
$ 176,166.80
|
|
Contingency
|
$ 5,000.00
|
$ 0.00
|
|
Subtotal
|
$ 183,795.88
|
$ 176,166.80
|
|
|
|
|
|
Eng/Admin/Legal
|
$ 30,000.00
|
$ 25,558.72
|
|
Total Estimated Project Cost
|
$ 213,795.88
|
$ 201,725.52
|
|
|
|
|
|
FUNDING
|
|
|
|
Park Development Fund
|
$ 197,329.87
|
$ 189,750.24
|
|
Tree Replacement Fund
|
$ 16,466.01
|
$ 11,975.28
|
|
Total Funding
|
$ 213,795.88
|
$ 201,725.52
|
| | |
|