Shakopee City Council
AprilĀ 5, 2022


FROM:Ryan Halverson, Assistant City Engineer
TO:Mayor and Council Members
Subject:

Final Contract Payment for the 12th Avenue Reconstruction Project

Policy/Action Requested:
Adopt Resolution R2022-049, accepting work on the 12th Avenue Reconstruction Project CIF-19-004, and authorizing final payment of $203,867.34 to S.M. Hentges & Sons.
Recommendation:
Adopt Resolution R2022-049.
Discussion:

On May 7, 2019, City Council awarded a contract for the 12th Avenue Reconstruction Project to S.M. Hentges & Sons.

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $2,869,489.38 with final contract amount of $2,800,588.73. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to S.M. Hentges & Sons in the amount of $203,867.34.

Budget Impact:

The total final project amount is $3,756,958.81. The project is funded by the Canterbury Commons Development Tax Increment Funding and by Shakopee Public Utilities. The following table provides a summary of the costs and funding comparing the estimated amount based on bid award versus the final actual amounts.

 

 

Estimate Based

Final Project

 

On Bid Award

Costs

COSTS

 

 

Construction Cost

$ 2,869,489.38

$ 2,866,531.98

Contingency

$    143,000.00

$    117,336.40

Subtotal

$ 3,012,489.38

$ 2,983,868.38

 

 

 

Easements

$    100,000.00

$      63,776.44

Eng/Admin/Legal

$    712,000.00

$    709,313.99 

Total Estimated Project Cost

$ 3,824,489.38

$ 3,756,958.81

 

 

 

FUNDING

 

 

Canterbury Commons TIF

$ 3,824,489.38

$ 3,750,236.41

Shakopee Public Utilities

$               0.00

$        6,722.40

Total Funding

$ 3,824,489.38

$ 3,756,958.81

 

The final contingency amount covered the costs of the 12th Avenue street light system, which wasn't included in the project estimate at time of award, and costs associated with a temporary traffic signal for detoured traffic around Canterbury Park during the closure of 12th Avenue.