| | | | | | | |  Shakopee City Council AprilĀ 5, 2022
|
| | | | | | | | | FROM: | Ryan Halverson, Assistant City Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject:
Final Contract Payment for the 12th Avenue Reconstruction Project | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2022-049, accepting work on the 12th Avenue Reconstruction Project CIF-19-004, and authorizing final payment of $203,867.34 to S.M. Hentges & Sons. | | |
| | | | | | | | Recommendation: Adopt Resolution R2022-049. | | |
| | | | | | | | Discussion:
On May 7, 2019, City Council awarded a contract for the 12th Avenue Reconstruction Project to S.M. Hentges & Sons.
All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $2,869,489.38 with final contract amount of $2,800,588.73. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to S.M. Hentges & Sons in the amount of $203,867.34. | | |
| | | | | | | | Budget Impact:
The total final project amount is $3,756,958.81. The project is funded by the Canterbury Commons Development Tax Increment Funding and by Shakopee Public Utilities. The following table provides a summary of the costs and funding comparing the estimated amount based on bid award versus the final actual amounts.
|
|
Estimate Based
|
Final Project
|
|
|
On Bid Award
|
Costs
|
|
COSTS
|
|
|
|
Construction Cost
|
$ 2,869,489.38
|
$ 2,866,531.98
|
|
Contingency
|
$ 143,000.00
|
$ 117,336.40
|
|
Subtotal
|
$ 3,012,489.38
|
$ 2,983,868.38
|
|
|
|
|
|
Easements
|
$ 100,000.00
|
$ 63,776.44
|
|
Eng/Admin/Legal
|
$ 712,000.00
|
$ 709,313.99
|
|
Total Estimated Project Cost
|
$ 3,824,489.38
|
$ 3,756,958.81
|
|
|
|
|
|
FUNDING
|
|
|
|
Canterbury Commons TIF
|
$ 3,824,489.38
|
$ 3,750,236.41
|
|
Shakopee Public Utilities
|
$ 0.00
|
$ 6,722.40
|
|
Total Funding
|
$ 3,824,489.38
|
$ 3,756,958.81
|
The final contingency amount covered the costs of the 12th Avenue street light system, which wasn't included in the project estimate at time of award, and costs associated with a temporary traffic signal for detoured traffic around Canterbury Park during the closure of 12th Avenue. | | |
|