| | | | | | | |  Shakopee City Council October 3, 2023
|
| | | | | | | | | FROM: | Micah Heckman, Assistant City Engineer | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject:
Jennifer Lane Park Project Closeout | | |
| | | | | | | | Policy/Action Requested: Adopt Resolution R2023-112, accepting work on the Jennifer Lane Park Project, PR-20-003, and authorize final payment in the amount of $2,024.32 to BKJ Land Co. II, Inc., dba BKJ Excavating. | | |
| | | | | | | | Recommendation: Adopt Resolution R2023-112. | | |
| | | | | | | | Discussion:
On July 6, 2021, City Council adopted Resolution R2021-105 accepting the bids and awarding the contract for the Jennifer Lane Park Project to BKJ Land Co. II, Inc. dba BKJ Excavating ("BKJ Excavating"), of Jordan, Minnesota.
All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $178,174.86 with actual final contract costs of $202,431.06. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to BKJ Excavating, in the amount of $2,024.32. | | |
| | | | | | | | Budget Impact:
The total final project amount is $341,498.16. This project is funded by the Park Development Fund. The following table provides a summary of the costs and funding comparing the estimated amounts based on bid award versus the final actual amounts.
|
|
ESTIMATE BASED
|
|
|
|
ON BID AWARD
|
FINAL COSTS
|
|
COSTS
|
|
|
|
Playground Equipment
|
$ 109,482.36
|
$ 109,482.36
|
| Site Improvements |
$ 178,174.86 |
$ 202,431.06 |
| Contingency |
$ 12,000.00 |
$ - |
|
Subtotal
|
$ 300,157.22
|
$ 311,913.42
|
|
|
|
|
|
Eng/Admin/Legal
|
$ 29,000.00
|
$ 29,584.74
|
|
Total Project Cost
|
$ 329,157.22
|
$ 341,498.16
|
|
|
|
|
|
FUNDING
|
|
|
|
Park Development Fund
|
$ 329,157.22
|
$ 341,498.16
|
|
Total Funding
|
$ 329,157.22
|
$ 341,498.16
|
| | |
|