Item Coversheet

*4.B.2.


Shakopee City Council
May 2, 2023


FROM:Alexander Enyi, Senior Engineering Technician
TO:Mayor and Council Members
Subject:

Final Contract Payment for the Unbridled Avenue Project

Policy/Action Requested:
Adopt Resolution R2023-058, accepting work on the Unbridled Avenue Project (CIF-20-014, Project 11), and authorizing final payment of $207,648.20 to Geislinger & Sons Inc.
Recommendation:
Adopt Resolution R2023-058.
Discussion:

On April 21, 2020, City Council awarded a contract for the Unbridled Avenue Project (CIF-20-014, Project 11) to Geislinger & Sons Inc.

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $6,212,461.82 with final contract amount of $6,008,192.56. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to Geislinger & Sons Inc. in the amount of $207,648.20.

Budget Impact:

The total final project amount is $7,506,279.11. The project is funded by the Canterbury Commons Development Tax Increment Funding and by Scott County. The following table provides a summary of the costs and funding comparing the estimated amount based on bid award versus the final actual amounts.

 

 

Estimate Based

Final Project

 

On Bid Award

Costs

COSTS

 

 

Construction Cost

$            6,212,461.82

$            6,008,192.56

Contingency

$               500,000.00

$               208,920.82

Subtotal

$            6,712,461.82

$            6,217,113.38

 

 

 

Easements

$                   5,000.00

$                   6,983.00

Eng/Admin/Legal

$            1,169,003.00

$            1,282,182.73

Total Estimated Project Cost

$            7,886,464.82

$            7,506,279.11

 

 

 

FUNDING

 

 

Canterbury Commons TIF

$            7,886,464.82

$            7,414,912.56

Scott County

$                          0.00

$                 91,366.55

Total Funding

$            7,886,464.82

$            7,506,279.11

 

The final contingency amount covered the costs of the Unbridled Avenue street light system and relocation of a digital message sign (DMS), which weren't included in the project estimate at time of award.

ATTACHMENTS:
Description
Resolution R2023-058
Certificate of Completion