Discussion:
Maras Street LLC, property owner, and John Mesenbrink, applicant, have submitted an application for Preliminary and Final Plat of RELIAKOR SECOND ADDITION, located south of Hansen Avenue and just west of Maras Street extended.
The property owner is proposing a reconfiguration of existing properties into two new parcels that will be used for a new Shakopee Public Utilities Electric Substation. The property totals approx. 8 acres. The property is zoned Light Industry (I-1) and guided Industrial.
The property owner’s consultant has developed a concept plan for the new building and it appears to comply with the I-1 Zone design standards. The BOAA approved a CUP request on September 7, 2023 for the utility structure.
The applicant’s narrative is attached to this report, along with their Preliminary and Final Plat drawings.
Staff have reviewed this application and should the City Council approve this request, conditions have been incorporated into the Resolution to ensure compliance with all City and utility requirements.