Discussion:
Trail improvements along County Road 16 have been programmed by Scott County as part of their Transportation Improvement Program (TIP) and the City as part of it's Capital Improvement Plan (CIP). The proposed improvements include construction of a bituminous trail and Americans with Disabilities Act (ADA) improvements. The proposed improvements have been split into three segments as follows:
Segment 1 - County Highway 18 to Moraine Drive Emergency Access
Segment 2 - Moraine Drive Emergency Access to Portage Lane
Segment 3 - 565 feet west of Portage Lane to 140 feet east of Spring Lake Drive
Segments 1 and 2 will be built in 2023 while the county is developing the Moraine Addition housing development adjacent to Segment 1. The county will fully fund construction of Segment 1. The construction costs for Segment 2 will be split per the County's City Local Cost Participation Policy Table. This policy states that the city and county will evenly split the cost of trail projects.
Segment 3 will be a separate future project.
The Construction Cooperative Agreement, which codifies the responsibilities of each agency and is consistent with other city-county agreements, is attached.