*Final Plat of Canterbury Southwest Fourth Addition
Policy/Action Requested:
Adopt Resolution R2023-133, which approves a one-lot final plat in the Canterbury Southwest development to allow for the construction of a 9,600 square-foot commercial building. 
Recommendation:
Adopt the resolution as presented. 
Discussion:

Site Information: 

Address: 2871 Winner's Circle Drive 

Lot Area: 1.62 acres

Property Owner: Canterbury DBSV Development LLC

Zoning: Planned Unit Development (PUD)

2040 Comp. Plan: Entertainment 

 

Bryce Hotzler, representing Greystone Construction has applied for the final plat of Canterbury Southwest Fourth Addition to allow for the construction of a roughly 9,600 square-foot building to house Mr. Pigstuff restaurant and one or two additional tenant spaces.

 

The initial Canterbury Southwest PUD was approved in June of 2020. The development of each lot requires a PUD Amendment and a Final Plat. To date, the following developments have been constructed in Canterbury Southwest:

 

  • Greystone Construction corporate office
  • Omry apartments (nearing completion)
  • Badger Hill / Bravi's
  • Next Steps Learning Center (nearing completion)

 

The City Council recently approved an amendment to the Planned Unit Development, which approved the building design and the proposed site plan with minor changes. The site is currently an outlot and must be final platted prior to construction of a building. The applicant intends to submit a building permit application soon. 

 

A shared parking agreement will be utilized on the site to the east of this site (across Suzanne's Way). The applicant has submitted a draft agreement that allows for the use of 20 parking spaces after 5:00 p.m. on weekdays and all weekend. Staff believes at least 30 spaces must be available on the site to the east. Requirements related to shared parking in the resolution also include the following conditions: 

 

  • The parking spaces on the eastern site must be paved by the end of 2024 if construction of the building and associated parking area on the east site has not happened by then.
  • If required parking spaces for this site will be on the eastern site, those spaces must be available during construction of a future building on the eastern site. A parking area away from construction / staging may need to be available / fenced off for the duration of construction on the east site.
  • The availability time or number of spaces in the agreement may need to be amended if warranted by a future use by the parking requirements of City Code, which would be reviewed as part of a tenant build out / change of occupancy. 
Budget Impact:
N/A
ATTACHMENTS: