Item Coversheet

*5.E.4.


Shakopee City Council
November 7, 2023


FROM:Michael Kerski, Planning/Development Director
TO:Mayor and Council Members
Subject:
Change order for Windermere Park Construction
Policy/Action Requested:
Approve a change order for $46,423.50 for Miller Brothers Excavating additional soil correction for Windermere Park.
Recommendation:
Approve change order
Discussion:

The original plans from SRF showed one set of numbers for import and export and once the sitework began, the contractor and engineer found that there was significant organic soils present that could not support the proposed trails along with a large layer of boulders..

 

Miller Brothers Excavating is removing the topsoil and transporting it to Memorial Park for replacement topsoil in the demolition areas and will also haul the remaining portion to Public Works for use in city parks.

 

They will also be installing Geotextile Fabric in the path area to ensure stable pathway construction.

Budget Impact:
The change order will come out of the project's contingency.