Electrical Services Agreement with Shakopee Public Utilities for Lions Park for undergrounding of utilities.
Policy/Action Requested:
Approve Service Agreement with Shakopee Public Utilities for an estimated cost of $42,600
Recommendation:
Approve Agreement with SPU.
Discussion:

Lions Park was fed from an overhead line through the original SandVenture Pumphouse off of Adams Street.  The power then went through the pool area and branched out. 

 

This was a 50-year old service line that does not meet current standards.

 

The new service line will come off of a pole on the east side of the park, be undergrounded westerly through the park, bored under the driveway to a new pad mounted transformer that will be south of SandVenture.  There will be new service drops across the front of SandVenture to serve the building and other uses in the area.

 

SPU is providing the labor at no cost and the city will be paying for 75% of the cost of materials including cable and the transformer and SPU will pay 25%.  This will be funded out of Park Development.  

Budget Impact:
Paid for out of park development funds.