Axel Ohman (Mason) Change Orders for SandVenture
Policy/Action Requested:
Approve change orders for SandVenture totalling $284,006 for work completed and to be completed at SandVenture.
Recommendation:
Approve change order.
Discussion:

Axel Ohman, the masonry contractor for SandVenture, has either completed or will complete more than $284,000 of work at SandVenture.

 

The previous construction manager approved work on site that has been completed.  These changes were not approved by the city, however, the work is completed and has been reviewed by the new construction manager, Kraus Anderson, and approved as completed.  The city is responsible for payment and the contractor will also be completing the above grade work. KA priced out using another contractor for the above grade work and Axel was still substantially less.

 

The change orders are as follows:

 

Winter Conditions          $100,479

The contractor has provided a discount on this work.  The foundations were installed during the coldest period of the winter.  They have been inspected and work was properly completed and documented.  They did not need to be installed at that time but the construction manager moved forward with the work even though the new block had not been ordered yet.

 

Design Changes          $ 15,832

Changes made to the structural design after original bid

 

Installation of the Insulated Block   $101,823

The contractor had originally bid to install only grey concrete block.  The block is now integral color on the pool portion and a two piece insulated system.

 

Below Design Grade Changes               $ 28,346

Changes made to the structural design after original bid

 

Value Engineering Impacts                    $ 37,526

While more than $1,000,000 was removed from the overall costs and an additional $300,000 was engineered out, there were changes made to the foundation design.

 

Total   $284,006

 