Discussion:
Hansen Thorp Pellinen Olson (HTPO) developed plans and solicited bids for four pickleball courts to be constructed in Scenic Heights Park.
The courts were part of the original master plan as developed with the community. With the completion of the Sports Court and new trails later this year, the park will be complete per the Master Plan.
The Engineer's estimate was $412,871.
BKJ Excavating $323,488.75
Northwest Asphalt $379,954.85
Veit & Company $385,270.00
Grit Contracting $294,810.50
Urban Companies $459,948.90
Peterson Companies $482,044.14
HTPO recommends awarding the project to BKJ.