| | | | | | | |  Shakopee City Council AugustĀ 7, 2024
|
| | | | | | | | | FROM: | Michael Kerski, Planning/Development Director | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject: Extension of Kraus Anderson Contract until September 2024 | | |
| | | | | | | | Policy/Action Requested: Approve an extension for Kraus Anderson's site supervision until September 2024 at a cost up to $50,000 including general conditions. | | |
| | | | | | | | Recommendation: Approve extension. | | |
| | | | | | | | Discussion:
There have been a number of delays in the project and KA has not been able to move off the project as planned. They are still waiting on metal doors so the storefronts can be installed and the original masonry took longer than planned. They feel the project should be wrapped up in September.
They will also be coordinating the MAU installation and site completion including sidewalks and landscaping. | | |
|