Item Coversheet

*4.B.1.


Shakopee City Council
September 17, 2024


FROM:Josiah Ferguson, Graduate Engineer
TO:Mayor and Council Members
Subject:

2022 Lions Park Pickleball Court Project Final Acceptance and Payment

Policy/Action Requested:
Adopt Resolution R2024-118, accepting work on the 2022 Lions Park Pickleball Court Project, PR-21-004, and authorize final payment in the amount of $3,052.56 to BKJ Land Co. II, Inc., dba BKJ Excavating.
Recommendation:
Adopt Resolution R2024-118.
Discussion:

On September 6, 2022, the City Council adopted Resolution R2022-116 accepting the bids and awarding the contract for the 2022 Lions Park Pickleball Court Project to BKJ Land Co. II, Inc. dba BKJ Excavating ("BKJ Excavating"), of Jordan, Minnesota. 

 

All of the improvements have been constructed in accordance with the contract documents. Attached is the Certificate of Completion showing the original contract amount of $307,605.17 with actual final contract costs of $305,255.78. All required project documentation has been received and is compliant. The project will be closed out upon issuance of final payment to BKJ Excavating, in the amount of $3,052.56.

Budget Impact:

The total final project amount is $375,068.60. This project is funded by the Park Development Fund. The following table provides a summary of the costs and funding comparing the estimated amounts based on bid award versus the final actual amounts.

 

COSTS

ESTIMATE BASED ON BID AWARD

FINAL COSTS

Park Furnishings

$ 32,672.92

$ 32,672.92

Construction Costs

$ 307,605.17

$ 305,255.78

Fence Modification

$ -

$ 11,206.88

Contingency

$ 15,000.00

$ -

Subtotal

$ 355,278.09

$ 349,135.58

 

 

 

Eng/Admin/Legal

$ 27,000.00

$ 25,993.02

Total Project Cost

$ 382,278.09

$ 375,068.60

 

 

 

FUNDING

 

 

Park Development Fund

$ 382,278.09

$ 375,068.60

Total Funding

$ 382,278.09

$ 375,068.60

 

 

 

 


ATTACHMENTS:
Description
Resolution R2024-118
Certificate of Completion