Item Coversheet

7.B.


Shakopee Park and Recreation Advisory Board
April 9, 2018


FROM: Michael Kerski, Director of Planning and Development 
TO:PRAB Members
Subject:
Review Preliminary Plat of Canterbury Park 7th Addition and Park Dedication Fees. 
Policy/Action Requested:
Recommend to the City Council acceptance of Park Dedication Fees at a rate of $2225 per unit for approximately 300 units in the first phase of the Doran development.
Recommendation:
Make recommendation to City Council.
Discussion:

Doran Canterbury I, LLC has made application to amend a PUD Overlay District for a proposed mixed use development, and approve the Preliminary Plat of Canterbury Park 7th Addition. The subject property is approximately 24 acres, and is located North of Eagle Creek Blvd., South of 4th Avenue East, & East of 3001 Eagle Creek Blvd.

The property is guided as entertainment, and is zoned Major Recreation (MR) Zone, and is included in the Canterbury Park Planned Unit Development (PUD). The proposal will introduce a residential development element to the project area, which will require a Vacation of Public Right-of-way/drainage & utility easements and a PUD Amendment. The City Council approved a Comprehensive Plan Amendment that allows up to 28 DUA in the Entertainment guided areas and in MR Zone when it is in a PUD.  

 

The PUD Amendment would establish residential use in the Canterbury Park development. 

The first phase of the project will involve the construction of a 295 unit apartment complex, along with a Club House and Gate House on a 13.3 acre parcel  The applicant is also proposing a perimeter 6’-0” fence, with gated entrances on the east and south sides of the complex. The second phase of the apartment project will include 304 additional units, and numerous amenities. The structures will have a perimeter driveway, and buildings are setback at least 60 feet from all property lines. There will be an extensive trail network, and the proposed Shenandoah Drive will include several roundabouts with significant landscaping and other decorative features.

Considerations

 

Applicant will be paying park dedication fees of $2225 per unit for the first phase.  The master developer of Canterbury will be completing the trail adjacent to the first phase connecting the neighborhood to the adjacent trail through an existing city-owned parcel.  The new Shenandoah alignment includes landscaping, sidewalk and trail.

 


Budget Impact:
ATTACHMENTS:
Description
Park Planner Recommendation
Plans