| | | | | | | |  Shakopee City Council March 7, 2017
|
| | | | | | | | | FROM: | Bruce Loney | | TO: | Mayor and Council Members |
| | | |
| | | | | | | | Subject: Approve Construction Cooperative Agreement with Scott County on CSAH 78 and CH 79 Trail. | | |
| | | | | | | | Policy/Action Requested: Approve a motion authorizing the appropriate city officials to execute the attached Construction Cooperative Agreement with Scott County. | | |
| | | | | | | | Recommendation: Staff recommends approval of the agreement and the cost share proposal in order to complete the regional trail connection from CSAH 16 to CSAH 17. | | |
| | | | | | | | Discussion: Scott County has received federal funds to construct the regional trail connection on CH 79 from CH 16 to CSAH 78 and along CSAH 78 from CH 79 to Jennifer Lane. Attached is the cost participation split where the city and county are splitting the local match and the engineering costs. The local construction cost is $110,418.00 and the engineering cost is $45,935.00 for a total city cost of $156,353.00. Scott County Board will be considering this agreement at its March 7, 2017 board meeting. | | |
| | | | | | | | Budget Impact: In the 2017-2921 Capital Improvement Program this project had $120,000.00 budgeted from the Capital Improvement fund. Also there is a budget impact to the general fund for future maintenance of the trail as per the agreement. | | |
|